Za’atari Refugee Camp Water and Waste water Networks – Phase II including Maintenance & Operation

Jun 2018

Project Name

Za’atari Refugee Camp Water and Waste water Networks – Phase II including Maintenance & Operation.

Owner

UNICEF.

Consultant

GITEC Consult GMBH and CEC.

Project Period

30 Months.

Description of Works

Construction of six Water Pump Station. Rehabilitation of three Water Pump Station, Construction of two Waste Water Pump Stations with emergency tanks and Force Mains in addition to SCADA System forthe entire project. Maintain & operate the entire system, including electromechanical works.