Project Name
Rehabilitation of Shmesani Pumping Station.
Owner
Water Authority of Jordan-WAJ.
Consultant
Jordan Water Company-Miyahuna LLC.
Project Period
151 days.
Description of Works
Rehabilitation of Shmesani Pumping Station by removing existing pumps and electrical panels,replace existing DN400 suction line with DN600 steel line, Supply and install new pumps (2x 500m3/hr-120mh + 1x 500m3/hr-80mh), Supply and install new MDB (2x 2000A incomers with bus coupler), Supply and install new low harmonic VFDs (2x250kW + 1x160kW) and Renovate station interior (offices, kitchen and bathroom, station floor, walls …etc).