+962 79 8255534 info@deraya-group.org

Purchase of smart meters/replacement of agricultural units in the Qaa Al-Sa’ideen irrigation project

Jan 2025

Project Name

Purchase of smart meters/replacement of agricultural units in the Qaa Al-Sa’ideen irrigation project.

Owner

Wadi Araba Development Company.

Consultant

Wadi Araba Development Company.

Project Period

60 days.

Description of Works

Supply, installation and equipping electrically and mechanically of 60 units of smart irrigation hydrants including flow meter, shut off valves, flow limiting device and control module all protected in ss enclosure in addition to supply spare parts for existing smart irrigation hydrants installed in Rahma and beer mathkour projects.