Project Name
Host Community Critical Water Supply 2020-Jaber Pumping Station Rehabilitation.
Owner
Jordan Yarmouk Water Company & WAJ.
Consultant
ICRC-International Committee of the Red Cross.
Project Period
150 days.
Description of Works
Rehabilitation of pump station forJaber well#10 in Ramtha Municipality, as follows: Foundation works forthe filtration unit, transporting of exist filtrationunit in the old site of Jaber Al-Balad with the new site of Jaber Al-Sarhan well#10, supplying water feed pumps forthe filtration unit,valves, piping, Aeration tower, electrical Panels, etc. and other works to put the pump station for it’s required operation & supplying 50m^3 steel watertank.