Separation of Potable Water Network

Jan 2025

Project Name

Separation of Potable Water Network.

Owner

Airport International Group-AIG.

Consultant

Airport International Group-AIG.

Project Period

120 days.

Description of Works

Separate the potable water network from the firefighting network by constructing a new pumping station dedicated to supplying the potable waterto the terminal building and other QAIA facilities, including the civil works such as excavation, casting concrete, building the pumping station, and all mechanical work such as supply and install pumps, valves, pipes…etc… The works also include testing and commissioning of the new pumps, and the required training.