Project Name
Supply and Installation of Wala and Lib Pumps in Wala and Lib Pump Stations.
Owner
Water Authority of Jordan.
Consultant
Jordan Water Company-Miyahuna LLC.
Project Period
120 days.
Description of Works
Replacement of 2 Pumps at Wala and 4 pumps at Lib Pump Stations with new 800m3/hr-235mh high efficiency pumps, install 4 new 800kW low harmonic VFDs & two 800kW soft starters, Supply and install 2x DN200 washout lines for Lib and Walah PS in addition to Supply 6 other pumps for Miyahuna Warehouse and Carry out necessary civil works forthe pumps and forthe wash out systems.